Kindly note the Change in PAY IN for BSE A/C No. : 1201250000000691 (CDSL), if you have an NSDL A/C, kindly use INTER DEPOSITORY SLIP. For assistance, please call OR contact: Mr. Dadu, 98339 89807 / 022-6145 1000.    |   Exchanges / Depository: Prevent Unauthorized Transactions in your Trading / Demat account --> Update your Mobile Numbers / email IDs with your Stock Brokers / Depository Participant. Receive alerts on your Registered Mobile / email IDs for trading account transactions and all debit and other important transactions in your demat account directly from Exchange / Depository on the same day ......................Issued in the interest of Investors."     |    KYC : "KYC is one time exercise while dealing in securities markets - once KYC is done through a SEBI registered intermediary (broker, DP, Mutual Fund etc.), you need not undergo the same process again when you approach another intermediary."     |    ASBA-IPO : "No need to issue cheques by investors while subscribing to IPO. Just write the bank account number and sign in the application form to authorise your bank to make payment in case of allotment. No worries for refund as the money remains in investor's account."
 ««+1  ««-1
 
BHEL commissions hydroelectric project in Bhutan     Back
(09 Jan 2025)
The said project was executed under a bilateral agreement between the Government of India and the Royal Government of Bhutan. PHEP-II is a greenfield hydroelectric project located in the Wangdue district of Western Bhutan.

The Francis Turbine installed at the site is designed to operate at a rated head of 241 meters, which is the highest for any Francis Type Hydro Turbine in Bhutan. Upon the full commissioning of all six units, the expected annual power generation will be 4,357 gigawatt-hours.

Unit 1 and 2 of the 6×170 MW PHEP-II were synchronised on December 16 and 17, 2024, respectively. BHEL's scope in PHEP-II comprises design, manufacture, supply, installation, and commissioning of electro-mechanical works for 6x170 MW vertical Francis turbines & matching synchronous generators, a control & monitoring (SCADA) system, generator transformers, shunt reactors, busducts, pothead yards, and associated auxiliaries.

The equipment for the project was supplied by BHEL’s units in Bhopal, Jhansi, Rudrapur, Bengaluru, and its transmission business group. Erection and commissioning on-site were carried out by the company's Power Sector-Eastern Region division based in Kolkata.

“BHEL has executed major projects like 4x84 MW Chukha, 4x15 MW Kurichhu, 6x170 MW Tala and 4x180 MW Mangdechhu in Bhutan till date. With the commissioning of these two units at PHEP-II, BHEL’s contribution to the total installed capacity in Bhutan now stands at nearly 89%. Further strengthening its footprint in the region, BHEL is currently executing an order for 6x200 MW Punatsangchhu-I HEP, in addition to PHEP-II in Bhutan,” stated in the company's regulatory filing.

State-run Bharat Heavy Electricals (BHEL) is engaged in the design, engineering, construction, testing, commissioning, and servicing of a wide range of products and services to the core sectors of the economy. As of 30 September 2024, the Government of India held a 63.17% stake in the company.

The scrip shed 0.95% to currently trade at Rs 221.10 on the BSE.